Search found 56 matches

by djean0001
Thu May 09, 2019 10:45 am
Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
Topic: Week #14: (4/22-26) Progress Reports.
Replies: 4
Views: 2673

Re: Week #14: (4/22-26) Progress Reports.

This week, we worked about the issue we had last week. With a long diagnostic, Boutin found we used a wrong terminal bus installed on the PLC so all the labels were wrong. Immediately we switched it to a correct one and everything works right. The robot did some movements and fixed the warehouse so ...
by djean0001
Thu May 09, 2019 10:23 am
Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
Topic: Week #13: (4/15-19) Progress Reports
Replies: 5
Views: 3057

Re: Week #13: (4/15-19) Progress Reports

This week, we had Mondays holiday and Thursdays no class, so, we missed some work to do. But, on Wednesday, we tried to get connected and started the way to establish communication between the Plc and HMI. We worked with Chuck to know how to prepare HMI and found out about some wiring issues on the ...
by djean0001
Thu May 02, 2019 5:11 pm
Forum: EET-260 Lab
Topic: Weeks # 12, 13 & 14 StampWorks Projects.
Replies: 5
Views: 3190

Re: Weeks # 12, 13 & 14 StampWorks Projects.

I completed the rest of the experiments 31, 32, and 33
by djean0001
Thu May 02, 2019 5:11 pm
Forum: EET-260 Lab
Topic: Week #11: (4/1-5) StampWorks Week #4
Replies: 6
Views: 3534

Re: Week #11: (4/1-5) StampWorks Week #4

I completed experiments 21 and 22. Attached is a screenshot from experiment 22
by djean0001
Thu May 02, 2019 5:10 pm
Forum: EET-260 Lab
Topic: Week #10: (3/25-29) StampWorks - Week #3
Replies: 4
Views: 2776

Re: Week #10: (3/25-29) StampWorks - Week #3

I have finished experiments 17 and 18. Attached is the pictures for those experiments
by djean0001
Wed May 01, 2019 4:02 pm
Forum: EET-250 Lab
Topic: Week #11: (4/1-5) Process Control Week #5.
Replies: 5
Views: 3614

Re: Week #11: (4/1-5) Process Control Week #5.

The Labs of this week has been completed.
by djean0001
Mon Apr 22, 2019 3:58 pm
Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
Topic: Week #12: (4/8-12) Progress Reports.
Replies: 6
Views: 3632

Re: Week #12: (4/8-12) Progress Reports.

Finally, the older translation table for the old existing project can be used. The robot is stable to do some movements such as reach the storage with the product in the gripper to the storage cell. So, we have a working table for the robot and try to go forward. To improve the communication between...
by djean0001
Mon Apr 22, 2019 3:23 pm
Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
Topic: Week #11: (4/1-5) Progress Reports
Replies: 6
Views: 3409

Re: Week #11: (4/1-5) Progress Reports

After many hours working on it, the translation table was shacked and was not a success so we started to brain storm what we were going to use instead of our custom made one. About The robot programing, it is underway in means of communication some minor moves were made. We tried to find help to imp...
by djean0001
Tue Apr 09, 2019 3:54 pm
Forum: EET-250 Lab
Topic: Week #10: (3/25-29) Process Control - Week #4
Replies: 5
Views: 3582

Re: Week #10: (3/25-29) Process Control - Week #4

You told us to skip chapter 5 and work on chapter 6.
by djean0001
Tue Apr 09, 2019 3:51 pm
Forum: EET-250 Lab
Topic: Week #9: (3/18-22) Process Control - Week #3
Replies: 5
Views: 3431

Re: Week #9: (3/18-22) Process Control - Week #3

Chapter 4 has been skipped to continue to 6.
by djean0001
Fri Apr 05, 2019 11:31 am
Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
Topic: Week #10: (3/25-29) Progress Reports
Replies: 6
Views: 3571

Re: Week #10: (3/25-29) Progress Reports

On 3/24- 29 week
We continued to wire from PLC to the conveyor. Improve the way the robot will move.
We discussed about the number of inputs and outputs to use and ease the robot job. We also received the materials to build the table.
by djean0001
Tue Apr 02, 2019 3:18 pm
Forum: EET-260 Lab
Topic: Week #9: (3/18-22) StampWorks Experiments #2.
Replies: 6
Views: 4855

Re: Week #9: (3/18-22) StampWorks Experiments #2.

Experiments # 2 Complete DJ 4/02/19
experiments 12,13,14,16
here is the screen shot from experiment 16 the frequency measurement
exp_16.png
exp_16.png (21.91 KiB) Viewed 4832 times
by djean0001
Thu Mar 28, 2019 2:26 pm
Forum: EET-260 Lab
Topic: Week #7: (3/4-8) StampWorks Experiments #1
Replies: 8
Views: 4377

Re: Week #7: (3/4-8) StampWorks Experiments #1

Lab experiment #26 has been started.
Experiments 27,28,10,11 Complete 4/2/19

"Verified 3/28/19 by RJ"
by djean0001
Tue Mar 26, 2019 4:39 pm
Forum: EET-250 Lab
Topic: Week #7: (3/4-8) Parallax Process Control - Week #2
Replies: 7
Views: 4700

Re: Week #7: (3/4-8) Parallax Process Control - Week #2

Process Control Labs has been completed
Data_Mon.jpg
Data_Mon.jpg (94.57 KiB) Viewed 4654 times
SIC Process Control -- Transistor DC Load Line.jpg
SIC Process Control -- Transistor DC Load Line.jpg (80.23 KiB) Viewed 4655 times
SIC Process Control -- Data Monitoring.jpg
SIC Process Control -- Data Monitoring.jpg (84.28 KiB) Viewed 4655 times
by djean0001
Tue Mar 26, 2019 1:28 pm
Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
Topic: Week #9: (3/18-22) Progress Reports
Replies: 6
Views: 3593

Re: Week #9: (3/18-22) Progress Reports

3/21/2019 We rewired the warehouse storage to establish the relation between PLC, Robot, and HMI. We improved the Flowchart of the project. We submitted an order for some materials to use for the translation table. We discussed about the use of some limit switchs and materials for the move of the ro...
by djean0001
Tue Mar 19, 2019 3:13 pm
Forum: EET-260 Lab
Topic: Week #6: (2/25-3/1) BS2 I/O Signals
Replies: 5
Views: 3520

Re: Week #6: (2/25-3/1) BS2 I/O Signals

Lab Complete I/O Signals on the Bs2
high_low_pause.png
high_low_pause.png (26.69 KiB) Viewed 3480 times
high_low_pause_25DC_40hz.png
high_low_pause_25DC_40hz.png (25.87 KiB) Viewed 3480 times
puls_out1.png
puls_out1.png (26.59 KiB) Viewed 3480 times
w/ 850 value
puls_out2.png
puls_out2.png (26.22 KiB) Viewed 3480 times
pulsin_01.png
pulsin_01.png (28.45 KiB) Viewed 3480 times
rc_time_2.png
rc_time_2.png (29.53 KiB) Viewed 3480 times
freqout.png
freqout.png (29.31 KiB) Viewed 3480 times
by djean0001
Tue Mar 05, 2019 9:56 am
Forum: EET-260 Lab
Topic: Week #3: (2/4-8) WAM Chapters 5 & 6
Replies: 8
Views: 4648

Re: Week #3: (2/4-8) WAM Chapters 5 & 6

The chapters 5-6 have been completed and one part of 7.
by djean0001
Thu Feb 28, 2019 9:23 am
Forum: EET-260 Lecture
Topic: Exam #1 Information
Replies: 12
Views: 6691

Re: Exam #1 Information

2/20/ 2019 I began working on the traffic light exam 1.
All 3 parts have been demonstrated by me to Rick on 03/08/2019.
by djean0001
Thu Feb 21, 2019 3:18 pm
Forum: EET-250 Lab
Topic: Week #5: (2/19-22) DACs and ADCs
Replies: 7
Views: 4339

Re: Week #5: (2/19-22) DACs and ADCs

This is the lab DACs and ADCs completed.