I am beginning this final
- Thu May 09, 2019 9:11 am
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #16: (5/6-10) Progress Reports
- Replies: 1
- Views: 2307
Re: Week #16: (5/6-10) Progress Reports
Tuesday May 7: Today we were doing more with the PLC program. We are still having a lot of issues with getting it to work. On Thursday we are hoping we can finally move forward. Thursday May 9:Today we made a lot of progress. We can now grab from all nine spots in the warehouse and place on out goin...
- Thu May 02, 2019 5:07 pm
- Forum: EET-260 Lab
- Topic: Weeks # 12, 13 & 14 StampWorks Projects.
- Replies: 5
- Views: 3238
Re: Weeks # 12, 13 & 14 StampWorks Projects.
I completed the rest of the experiments 31, 32, and 33.
- Thu May 02, 2019 5:07 pm
- Forum: EET-260 Lab
- Topic: Week #11: (4/1-5) StampWorks Week #4
- Replies: 6
- Views: 3587
Re: Week #11: (4/1-5) StampWorks Week #4
I completed experiments 21 and 22. Attached is a screenshot from experiment 22.
- Thu May 02, 2019 5:05 pm
- Forum: EET-260 Lab
- Topic: Week #10: (3/25-29) StampWorks - Week #3
- Replies: 4
- Views: 2815
Re: Week #10: (3/25-29) StampWorks - Week #3
I have finished experiments 17 and 18. Attached is the pictures for those experiments.
- Thu May 02, 2019 3:28 pm
- Forum: EET-260 Lab
- Topic: Week #9: (3/18-22) StampWorks Experiments #2.
- Replies: 6
- Views: 4960
Re: Week #9: (3/18-22) StampWorks Experiments #2.
I have finished experiments 12, 13 ,14 and 16. Attached if the screenshot from experiment 16.
- Thu May 02, 2019 1:34 pm
- Forum: EET-250 Lab
- Topic: Week #12: (4/8-12) Process Control Week #6
- Replies: 3
- Views: 2707
Re: Week #12: (4/8-12) Process Control Week #6
I am caught up to this week.
- Wed May 01, 2019 9:21 pm
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #15: (4/29-5/3) Progress Reports.
- Replies: 4
- Views: 2860
Re: Week #15: (4/29-5/3) Progress Reports.
Tuesday April 30: Today Chris and dave worked in getting the program written on the PLC to communicate to the robot to have it do certain moves. Later in the day we were able to make the block of wood go to the end on the intake conveyor and trigging the limit switch and stop the conveyor and start ...
- Tue Apr 23, 2019 10:04 pm
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #14: (4/22-26) Progress Reports.
- Replies: 4
- Views: 2700
Re: Week #14: (4/22-26) Progress Reports.
Tuesday April 23: Chris, Dave, and I were trying to diagnose a problem that we were having with our inputs on our PLC. I finally figured out that everything was wired right, HOWEVER the wrong terminal bus was installed on the PLC so all the labels were wrong. Once we switched it to the correct one e...
- Mon Apr 22, 2019 11:05 am
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #13: (4/15-19) Progress Reports
- Replies: 5
- Views: 3092
Re: Week #13: (4/15-19) Progress Reports
This week we only had Tuesday and i was able to get some more of the moves on the robot done. The retrieving the block from the incoming conveyor is done and the placing in the warehouse rack is almost finished. i plan to have the place and retrieving in the warehouse rack done by next week.
- Sun Apr 14, 2019 8:45 am
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #12: (4/8-12) Progress Reports.
- Replies: 6
- Views: 3672
Re: Week #12: (4/8-12) Progress Reports.
At this point the robotic program for communicating with the plc is complete as well as the first move. The second move has been started just a few minor adjustment s needed. We also got everything screwed down to the table in its Permanent location. We are getting closer!
- Sun Apr 14, 2019 8:42 am
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #11: (4/1-5) Progress Reports
- Replies: 6
- Views: 3447
Re: Week #11: (4/1-5) Progress Reports
This week I got the program for the robot to communicate with the old done. Then I also got the 1st move programmed. However we didn’t have our translation table built yet so next week I will have to adjust the movement around to accommodate for the height of the translation table.
- Sun Apr 14, 2019 8:40 am
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #10: (3/25-29) Progress Reports
- Replies: 6
- Views: 3616
Re: Week #10: (3/25-29) Progress Reports
This week we ordered some parts for our translation table. We also figure out how we were going to communicate from the robot to the plc. I got some of the robot programming done as well.
- Thu Apr 04, 2019 4:38 pm
- Forum: EET-260 Lab
- Topic: Week #7: (3/4-8) StampWorks Experiments #1
- Replies: 8
- Views: 4422
Re: Week #7: (3/4-8) StampWorks Experiments #1
I have completed Experiments 26 and 27 10 and 11 so far on 4/4/2019.
- Tue Apr 02, 2019 2:32 pm
- Forum: EET-250 Lab
- Topic: Week #11: (4/1-5) Process Control Week #5.
- Replies: 5
- Views: 3657
Re: Week #11: (4/1-5) Process Control Week #5.
I have finished the lab for this week. Here are the screenshots.
- Tue Apr 02, 2019 2:29 pm
- Forum: EET-250 Lab
- Topic: Week #10: (3/25-29) Process Control - Week #4
- Replies: 5
- Views: 3627
Re: Week #10: (3/25-29) Process Control - Week #4
You told me to skip chapter 5 for now and work on chapter 6.
- Mon Apr 01, 2019 11:19 am
- Forum: EET-250 Lab
- Topic: Week #9: (3/18-22) Process Control - Week #3
- Replies: 5
- Views: 3469
Re: Week #9: (3/18-22) Process Control - Week #3
We were told to skip chapter 4 for now.
- Thu Mar 28, 2019 4:01 pm
- Forum: EET-250 Lab
- Topic: Week #7: (3/4-8) Parallax Process Control - Week #2
- Replies: 7
- Views: 4749
Re: Week #7: (3/4-8) Parallax Process Control - Week #2
I have completed the lab for this week. here are the screenshots.
- Thu Mar 28, 2019 8:47 am
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #7: (3/4-8) Progress Reports
- Replies: 5
- Views: 3345
Re: Week #7: (3/4-8) Progress Reports
We discussed a few different ideas briefly. however we all got side tracked by the Traffic light project.
- Thu Mar 28, 2019 8:47 am
- Forum: Weekly Progress Reports - Warehouse Storage/Retrieval
- Topic: Week #6: (2/25-3/1) Progress Reports
- Replies: 5
- Views: 3159
Re: Week #6: (2/25-3/1) Progress Reports
We discussed a few different ideas briefly. however we all got side tracked by the Traffic light project.