Worked with Eric LeDuc
viewtopic.php?p=9925#p9925
Search found 52 matches
- Tue Apr 30, 2024 3:28 pm
- Forum: EET-250 Lab
- Topic: Week #12 (4/8-12): Parallax Process Control - Week #5.
- Replies: 5
- Views: 373
- Tue Apr 30, 2024 3:26 pm
- Forum: EET-250 Lab
- Topic: Week #11 (4/1-5): Parallax Process Control - Week #4
- Replies: 12
- Views: 709
- Tue Apr 30, 2024 3:24 pm
- Forum: EET-250 Lab
- Topic: Week #10 (3/25-29): Parallax Process Control - Week #3
- Replies: 11
- Views: 774
- Tue Apr 30, 2024 3:23 pm
- Forum: EET-250 Lab
- Topic: Week #7 & #9: (3/4-22) Parallax Process Control - Week #2
- Replies: 11
- Views: 715
Re: Week #7 & #9: (3/4-22) Parallax Process Control - Week #2
Worked with Eric LeDuc
viewtopic.php?p=9863#p9863
viewtopic.php?p=9863#p9863
- Tue Apr 30, 2024 3:21 pm
- Forum: EET-250 Lab
- Topic: Week #6: Intro to Parallax Process Control - Week #1
- Replies: 10
- Views: 529
Re: Week #6: Intro to Parallax Process Control - Week #1
Completed with Eric LeDuc
- Tue Apr 30, 2024 3:04 pm
- Forum: EET-250 Lab
- Topic: Week #5 (2/19-23): DACs & ADCs
- Replies: 9
- Views: 548
Re: Week #5 (2/19-23): DACs & ADCs
Will Henry
- Tue Apr 30, 2024 3:03 pm
- Forum: EET-250 Lab
- Topic: Week #4 (2/12-16): Differentiators & Integrators.
- Replies: 11
- Views: 556
- Tue Apr 30, 2024 2:58 pm
- Forum: EET-250 Lab
- Topic: Week #3 (2/5-9): Sensor Wiring & Testing
- Replies: 10
- Views: 637
Re: Week #3 (2/5-9): Sensor Wiring & Testing
Will Henry
- Tue Apr 30, 2024 2:57 pm
- Forum: EET-250 Lab
- Topic: Week #2 (1/29-2/2): Equipment Investigation, Troubleshooting & Repair
- Replies: 11
- Views: 831
- Tue Apr 30, 2024 2:53 pm
- Forum: EET-250 Lab
- Topic: Week #1 (1/22-26): 555 Timer
- Replies: 11
- Views: 1125
Re: Week #1 (1/22-26): 555 Timer
Will Henry
- Tue Apr 30, 2024 2:41 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #15 (4/29-5/3): Progress Reports
- Replies: 3
- Views: 176
Re: Week #15 (4/29-5/3): Progress Reports
Wired Fanuc, did not test. Made diagram
- Tue Apr 30, 2024 2:35 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #14 (4/22-26): Progress Reports.
- Replies: 4
- Views: 216
Re: Week #14 (4/22-26): Progress Reports.
Sourced CAT5e for more flexibility with Dobot motion. Wired new JST connectors. Dobot interfaces with HMI and PLC and sends signal.
Made Fanuc IO functional
Made Fanuc IO functional
- Tue Apr 30, 2024 2:33 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #13 (4/15-19) Progress Reports
- Replies: 4
- Views: 193
Re: Week #13 (4/15-19) Progress Reports
Settled on two JST plugs for 8 wires, interfaced Dobot with PLC and HMI, confirmed functionality. Rewrote Dobot program for consolidated wiring
- Tue Apr 30, 2024 2:31 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #12 (4/8-12): Progress Reports
- Replies: 4
- Views: 244
Re: Week #12 (4/8-12): Progress Reports
Played around with JST connections, ran PLC and HMI independent of PC
- Tue Apr 30, 2024 2:29 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #11 (4/1-5): Progress Reports
- Replies: 4
- Views: 229
Re: Week #11 (4/1-5): Progress Reports
Cut wood for housing
Assembled plug with JST connectors and CAT-6
Assembled plug with JST connectors and CAT-6
- Tue Apr 30, 2024 2:27 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #10 (3/25-29) Progress Reports
- Replies: 4
- Views: 235
Re: Week #10 (3/25-29) Progress Reports
Ran through PLC to confirm functionality, acquired JST connectors for Dobot
- Thu Apr 18, 2024 1:53 pm
- Forum: EET-250 Lab
- Topic: Week #11 (4/1-5): Parallax Process Control - Week #4
- Replies: 12
- Views: 709
Re: Week #11 (4/1-5): Parallax Process Control - Week #4
Will Henry Eric LeDuc
Chapter 6 Activity 3
Chapter 6 Activity 3
- Sat Mar 23, 2024 3:02 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #9 (3/18-3/22): Progress Reports
- Replies: 4
- Views: 259
Re: Week #9 (3/18-3/22): Progress Reports
PLC program is more or less complete, pending debugging. HMI is set up to reflect progress of program.
- Sat Mar 23, 2024 2:59 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #7 (3/4-3/8): Progress Reports
- Replies: 5
- Views: 282
Re: Week #7 (3/4-3/8): Progress Reports
Outlined outputs from PLC to Dobot/Fanuc. Established which PLC modules I'd use to have more outputs available.
- Sat Mar 23, 2024 2:55 pm
- Forum: Progress Reports for Vending Group
- Topic: Week #6 (2/26-3/1): Progress Reports
- Replies: 7
- Views: 322
Re: Week #6 (2/26-3/1): Progress Reports
Mostly completed HMI lock in of variables, mostly completed drink dispensing portion of PLC, outlined overall program