by asingh0001
Fri May 11, 2018 3:00 pm
Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
Topic: Week #16: (5/7-5/11) Progress Reports
Replies: 1
Views: 2048

Re: Week #16: (5/7-5/11) Progress Reports

We started working on the conveyor belt again. Also, wired all the LED's for the system and did testing again this week of all the stations.
Amrit
by asingh0001
Fri May 11, 2018 2:28 pm
Forum: EET-250 Lab
Topic: Week #9: (3/19-23) Process Control, Chapter 4
Replies: 3
Views: 2529

Re: Week #9: (3/19-23) Process Control, Chapter 4

I tried different sensors w/ different resistor values but nothing seemed to work.
The sensor was giving me a hard time.
Amrit
by asingh0001
Fri May 11, 2018 2:26 pm
Forum: EET-250 Lab
Topic: Week #13: (4/16-20) Process Control Chapter 8
Replies: 5
Views: 3331

Re: Week #13: (4/16-20) Process Control Chapter 8

Lab Completed.
Amrit
by asingh0001
Fri May 11, 2018 1:28 pm
Forum: EET-260 Lab
Topic: Week #7: (3/5-9) BS2 I/O Signals
Replies: 6
Views: 3817

Re: Week #7: (3/5-9) BS2 I/O Signals

Lab Completed.
Amrit
by asingh0001
Fri May 11, 2018 1:17 pm
Forum: EET-260 Lab
Topic: Week #6: (2/26-3/2) Finish WAM
Replies: 2
Views: 3182

Re: Week #6: (2/26-3/2) Finish WAM

WAM Book Completed.
Amrit
by asingh0001
Thu May 10, 2018 8:37 pm
Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
Topic: Week #15: (4/30-5/4) Progress Reports
Replies: 5
Views: 2998

Re: Week #15: (4/30-5/4) Progress Reports

Did testing and collabarated all HMI screen buttons with the system for perfect topping sizes. Also, worked with the team doing wire labelling.
by asingh0001
Wed May 09, 2018 3:03 pm
Forum: EET-260 Lab
Topic: Week #15: (4/30-5/4) Advanced Sensors
Replies: 5
Views: 3367

Re: Week #15: (4/30-5/4) Advanced Sensors

Lab Completed. ColorPal Flicker, Mimic, and Memsic Accelerometer.
Amrit


"Verified 5/9/18 by RJ"
by asingh0001
Wed May 09, 2018 2:25 pm
Forum: EET-260 Lab
Topic: Week #14: (4/23-27) PING Ultrasonic & 4x4 Keypad
Replies: 4
Views: 2802

Re: Week #14: (4/23-27) PING Ultrasonic & 4x4 Keypad

Lab Completed.
Amrit


"Verified 5/9/18 by RJ"
by asingh0001
Wed May 09, 2018 1:29 pm
Forum: EET-260 Lab
Topic: Week #13: (4/16-20) Truth Table Programming.
Replies: 3
Views: 2548

Re: Week #13: (4/16-20) Truth Table Programming.

Lab Completed.
Amrit


"Verified 5/9/18 by RJ"
by asingh0001
Sat May 05, 2018 12:28 pm
Forum: EET-255 Advanced Topics in EET/Automation
Topic: End of Year Assignment - Spring 2018 Evening Class
Replies: 9
Views: 4435

Re: End of Year Assignment - Spring 2018 Evening Class

I am Beginning the final Assignment.
Amrit
by asingh0001
Tue May 01, 2018 4:26 pm
Forum: EET-250 Lab
Topic: Week #12: (4/9-13) Process Control Chapter 7.
Replies: 9
Views: 5105

Re: Week #12: (4/9-13) Process Control Chapter 7.

Lab Completed.
Amrit
by asingh0001
Tue May 01, 2018 3:59 pm
Forum: EET-250 Lab
Topic: Week #11: (4/2-6) Process Control, Chapter 6.
Replies: 8
Views: 4810

Re: Week #11: (4/2-6) Process Control, Chapter 6.

Lab Completed.
Amrit
by asingh0001
Tue May 01, 2018 12:11 pm
Forum: EET-250 Lab
Topic: Week #7: Parallax Process Control
Replies: 8
Views: 4568

Re: Week #7: Parallax Process Control

Lab Completed
Amrit
by asingh0001
Mon Apr 23, 2018 11:20 am
Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
Topic: Week #11: (4/2-6) Progress Reports.
Replies: 7
Views: 3991

Re: Week #11: (4/2-6) Progress Reports.

Collaborated the sensors with PLC's using relays and made wiring schematics for the system.
by asingh0001
Mon Apr 23, 2018 10:49 am
Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
Topic: Week #12: (4/9-13) Progress Reports.
Replies: 7
Views: 3865

Re: Week #12: (4/9-13) Progress Reports.

Wired all the sensors for stations and did PLC Programming.
Amrit
by asingh0001
Mon Apr 23, 2018 10:48 am
Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
Topic: Week #13: (4/16-20) Progress Reports
Replies: 7
Views: 3861

Re: Week #13: (4/16-20) Progress Reports

Built a station for PLC, Panelview, and other electrical connection.
Amrit
by asingh0001
Fri Apr 20, 2018 10:38 am
Forum: EET-260 Lab
Topic: Week #12: (4/9-13) Stampworks Week #4
Replies: 8
Views: 4324

Re: Week #12: (4/9-13) Stampworks Week #4

Everything Done.
Amrit

"Verified 4/20/18 by RJ"
by asingh0001
Fri Apr 20, 2018 10:32 am
Forum: EET-260 Lab
Topic: Week #11: (4/2-6) StampWorks Experiments Week #3.
Replies: 5
Views: 3184

Re: Week #11: (4/2-6) StampWorks Experiments Week #3.

Experiments 22, 31,32, 33 Done.
Amrit

Verified 4/20/18 by RJ