We started working on the conveyor belt again. Also, wired all the LED's for the system and did testing again this week of all the stations.
Amrit
Search found 55 matches
- Fri May 11, 2018 3:00 pm
- Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
- Topic: Week #16: (5/7-5/11) Progress Reports
- Replies: 1
- Views: 2085
- Fri May 11, 2018 2:28 pm
- Forum: EET-250 Lab
- Topic: Week #9: (3/19-23) Process Control, Chapter 4
- Replies: 3
- Views: 2541
Re: Week #9: (3/19-23) Process Control, Chapter 4
I tried different sensors w/ different resistor values but nothing seemed to work.
The sensor was giving me a hard time.
Amrit
The sensor was giving me a hard time.
Amrit
- Fri May 11, 2018 2:26 pm
- Forum: EET-250 Lab
- Topic: Week #13: (4/16-20) Process Control Chapter 8
- Replies: 5
- Views: 3353
Re: Week #13: (4/16-20) Process Control Chapter 8
Lab Completed.
Amrit
Amrit
- Fri May 11, 2018 1:28 pm
- Forum: EET-260 Lab
- Topic: Week #7: (3/5-9) BS2 I/O Signals
- Replies: 6
- Views: 3834
Re: Week #7: (3/5-9) BS2 I/O Signals
Lab Completed.
Amrit
Amrit
- Fri May 11, 2018 1:17 pm
- Forum: EET-260 Lab
- Topic: Week #6: (2/26-3/2) Finish WAM
- Replies: 2
- Views: 3227
Re: Week #6: (2/26-3/2) Finish WAM
WAM Book Completed.
Amrit
Amrit
- Thu May 10, 2018 8:37 pm
- Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
- Topic: Week #15: (4/30-5/4) Progress Reports
- Replies: 5
- Views: 3017
Re: Week #15: (4/30-5/4) Progress Reports
Did testing and collabarated all HMI screen buttons with the system for perfect topping sizes. Also, worked with the team doing wire labelling.
- Wed May 09, 2018 3:03 pm
- Forum: EET-260 Lab
- Topic: Week #15: (4/30-5/4) Advanced Sensors
- Replies: 5
- Views: 3385
Re: Week #15: (4/30-5/4) Advanced Sensors
Lab Completed. ColorPal Flicker, Mimic, and Memsic Accelerometer.
Amrit
"Verified 5/9/18 by RJ"
Amrit
"Verified 5/9/18 by RJ"
- Wed May 09, 2018 2:25 pm
- Forum: EET-260 Lab
- Topic: Week #14: (4/23-27) PING Ultrasonic & 4x4 Keypad
- Replies: 4
- Views: 2831
Re: Week #14: (4/23-27) PING Ultrasonic & 4x4 Keypad
Lab Completed.
Amrit
"Verified 5/9/18 by RJ"
Amrit
"Verified 5/9/18 by RJ"
- Wed May 09, 2018 1:29 pm
- Forum: EET-260 Lab
- Topic: Week #13: (4/16-20) Truth Table Programming.
- Replies: 3
- Views: 2563
Re: Week #13: (4/16-20) Truth Table Programming.
Lab Completed.
Amrit
"Verified 5/9/18 by RJ"
Amrit
"Verified 5/9/18 by RJ"
- Sat May 05, 2018 12:28 pm
- Forum: EET-255 Advanced Topics in EET/Automation
- Topic: End of Year Assignment - Spring 2018 Evening Class
- Replies: 9
- Views: 4468
Re: End of Year Assignment - Spring 2018 Evening Class
I am Beginning the final Assignment.
Amrit
Amrit
- Tue May 01, 2018 4:26 pm
- Forum: EET-250 Lab
- Topic: Week #12: (4/9-13) Process Control Chapter 7.
- Replies: 9
- Views: 5126
Re: Week #12: (4/9-13) Process Control Chapter 7.
Lab Completed.
Amrit
Amrit
- Tue May 01, 2018 3:59 pm
- Forum: EET-250 Lab
- Topic: Week #11: (4/2-6) Process Control, Chapter 6.
- Replies: 8
- Views: 4839
Re: Week #11: (4/2-6) Process Control, Chapter 6.
Lab Completed.
Amrit
Amrit
- Tue May 01, 2018 12:11 pm
- Forum: EET-250 Lab
- Topic: Week #7: Parallax Process Control
- Replies: 8
- Views: 4590
Re: Week #7: Parallax Process Control
Lab Completed
Amrit
Amrit
- Tue May 01, 2018 11:47 am
- Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
- Topic: Week #14: (4/23-27) Progress Reports.
- Replies: 6
- Views: 3706
Re: Week #14: (4/23-27) Progress Reports.
Worked on the conveyor belt.
Amrit
Amrit
- Tue Apr 24, 2018 2:46 pm
- Forum: EET-250 Lab
- Topic: Week #6: (2/26-3/2) Introduction to Parallax Process Control
- Replies: 8
- Views: 4679
Re: Week #6: (2/26-3/2) Introduction to Parallax Process Control
Lab Completed.
Amrit
Amrit
- Mon Apr 23, 2018 11:20 am
- Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
- Topic: Week #11: (4/2-6) Progress Reports.
- Replies: 7
- Views: 4010
Re: Week #11: (4/2-6) Progress Reports.
Collaborated the sensors with PLC's using relays and made wiring schematics for the system.
- Mon Apr 23, 2018 10:49 am
- Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
- Topic: Week #12: (4/9-13) Progress Reports.
- Replies: 7
- Views: 3889
Re: Week #12: (4/9-13) Progress Reports.
Wired all the sensors for stations and did PLC Programming.
Amrit
Amrit
- Mon Apr 23, 2018 10:48 am
- Forum: Weekly Progress Reports - Post Weekly Progress Reports here.
- Topic: Week #13: (4/16-20) Progress Reports
- Replies: 7
- Views: 3883
Re: Week #13: (4/16-20) Progress Reports
Built a station for PLC, Panelview, and other electrical connection.
Amrit
Amrit
- Fri Apr 20, 2018 10:38 am
- Forum: EET-260 Lab
- Topic: Week #12: (4/9-13) Stampworks Week #4
- Replies: 8
- Views: 4354
Re: Week #12: (4/9-13) Stampworks Week #4
Everything Done.
Amrit
"Verified 4/20/18 by RJ"
Amrit
"Verified 4/20/18 by RJ"
- Fri Apr 20, 2018 10:32 am
- Forum: EET-260 Lab
- Topic: Week #11: (4/2-6) StampWorks Experiments Week #3.
- Replies: 5
- Views: 3213
Re: Week #11: (4/2-6) StampWorks Experiments Week #3.
Experiments 22, 31,32, 33 Done.
Amrit
Verified 4/20/18 by RJ
Amrit
Verified 4/20/18 by RJ