Week #2: (1/28-2/1) Scheduling, Sensors & Interfacing

Locked
rjagodowski
Posts: 2371
Joined: Fri Sep 04, 2015 6:59 pm

Week #2: (1/28-2/1) Scheduling, Sensors & Interfacing

Post by rjagodowski »

We will briefly discuss some scheduling concepts as you create a completion schedule for your Advanced Automation Project. Full discussion of Scheduling can be found Here, In Week #4 of EET-255 Advanced Topics In EET/Automation from last Spring.

Your group should submit a tentative schedule for your project by Friday, 2/2. This schedule should include the major construction tasks, an estimated timeline and who will be assigned to each task.

This week you a handout was distributed from Eaton Sensors. We will be using this for the next several weeks. Here is the pdf of that handout:
vol08_tab12_Sensor Learning Course.pdf
(1.06 MiB) Downloaded 182 times
You should read through this entire document within the next 3 weeks.
vrwhitcomb0001
Posts: 40
Joined: Wed Jan 30, 2019 8:15 pm

Re: Week #2: (1/28-2/1) Scheduling, Sensors & Interfacing

Post by vrwhitcomb0001 »

Advanced Automation Spring Project Schedule.docx
(12.73 KiB) Downloaded 178 times

Project schedule rough draft.
crlapan
Posts: 56
Joined: Tue Sep 12, 2017 10:19 am

Re: Week #2: (1/28-2/1) Scheduling, Sensors & Interfacing

Post by crlapan »

2019 Project Schedule.pdf
(119.06 KiB) Downloaded 165 times
Project Schedule Rough Draft Not Complete!!!
djean0001
Posts: 56
Joined: Tue Sep 12, 2017 1:38 pm

Re: Week #2: (1/28-2/1) Scheduling, Sensors & Interfacing

Post by djean0001 »

This is a tentative scheduling of our group after discussing together.
Attachments
2019 Project Schedule.pdf.docx
(1.02 MiB) Downloaded 161 times
Locked