Week #3: (2/4-8) Progess Reports.

Post Reply
rjagodowski
Posts: 2380
Joined: Fri Sep 04, 2015 6:59 pm

Week #3: (2/4-8) Progess Reports.

Post by rjagodowski »

Post your progress reports for Week #3 here.
ctboutin0001
Posts: 63
Joined: Mon Sep 18, 2017 9:18 am

Re: Week #3: (2/4-8) Progess Reports.

Post by ctboutin0001 »

Tuesday: 2/5/19 we further discussed exactly how we wanted everything to function. we discussed how we are going to use proximity sensors for help the robot know its location. we also came up with a list of things that we would need based off our plan. I downloaded the Dobot software and was able to fool around with the robot to get used to the new software and also to help us figure out where the robot how has to be. we also further discussed our schedule.

Thursday: 2/7/19 We adding all new sensors to the back of the warehouse shelving unit and got an idea of how high the robot will be sitting on the translation table so we could so the we would have to set the warehouse up so that the robot can reach all areas.once the translation stable is built we can go further with programing the robot.
Last edited by ctboutin0001 on Sat Feb 09, 2019 8:16 pm, edited 1 time in total.
almarafuga0001
Posts: 60
Joined: Fri Sep 15, 2017 9:18 am

Re: Week #3: (2/4-8) Progess Reports.

Post by almarafuga0001 »

Tuesday: 2/5/19 - Made up our plan and figured out our schedule for what each person needs to be working on.

Thursday: 2/7/19 - Rewired the old PLC to a better PLC and organized the wires as I did so.
crlapan
Posts: 56
Joined: Tue Sep 12, 2017 10:19 am

Re: Week #3: (2/4-8) Progess Reports.

Post by crlapan »

Week ending: 2/8/19 We further discussed exactly how we wanted everything to function. We discussed how we are going to use proximity sensors to help the robot know its location. I had the 3d part completed and we installed it on the dobot. We also came up with a list of things that we would need based off our plan. The project is coming along well and we began constructing our translation table for the robot. Group members rewired in our new PLC. We drew up a pictorial illustration of our design
Allen's Warehouse.pdf
(58.37 KiB) Downloaded 165 times
.And we revised our schedule
2019 Project Schedule_R1.pdf
(126.45 KiB) Downloaded 170 times
. We will have to shave our parts(wooden blocks) for the robot to grip them better. We began discussing and writing PLC program.
ajfranqui0001
Posts: 54
Joined: Mon Sep 25, 2017 10:29 am

Re: Week #3: (2/4-8) Progess Reports.

Post by ajfranqui0001 »

Tuesday: 2/5/19- We discussed and figured out the schedule for what each person needs to be working on.

Thursday: 2/7/19- Anthony and I rewired the old plc to better and bigger capacity plc and we also organized the wires.
djean0001
Posts: 56
Joined: Tue Sep 12, 2017 1:38 pm

Re: Week #3: (2/4-8) Progess Reports.

Post by djean0001 »

Week: 2/4-8/19 We assigned to each person what to do as a work in the project.

Date: 2/7/19, This week, we understood how better the way to place all elements on the table. For instance, where the Dobot robot can be placed, with it trail in wood, to pick up the items. We identified where to place all censors and Prox. we started to worked on software Ladder PLC and HMI PV to use.

We agree about the projected schedule outline following:
Attachments
2019 Project Schedule_R1.pdf.docx
(15.65 KiB) Downloaded 167 times
rgomez0001
Posts: 42
Joined: Tue Sep 11, 2018 12:50 pm

Re: Week #3: (2/4-8) Progess Reports.

Post by rgomez0001 »

Tuesday: 2/5/19 -(( short day snow day))Made our plan and figured out schedule for what each person needs to be working on, and how the plc 's flowchart should look with the help of chuck.

2/7/19; Made new congruent square base and new brick with three wholes for the table the robot will be sitting on. talked about colors and filed off sharp corner mainly trial and error until things looked perfect . also shaved off a yard off the wood on the metal poles to make it fit the table.