Week #10: (3/29-4/2) Parallax Process Control - Week #2
-
- Posts: 2382
- Joined: Fri Sep 04, 2015 6:59 pm
Week #10: (3/29-4/2) Parallax Process Control - Week #2
This week you will begin using the Parallax Process Control kits. The Process Control text and other documentation can be downloaded Week #9.
This week's lab exercise is to continue working in the Process Control text. You should have read and worked through Chapters 1 & 2 last week. If not, do so FIRST!!!
NOTE: StampPlot software IS NOT permanently installed on the computers in our lab. You need to follow the directions given in Week #9 and install it on your own computer or have your professor install it on the computer you are going to use. It is highly recommended that you install it on your own computer as you will be using StampPlot regularly for the rest of this course and creating numerous screenshots and files. Having this installed on your own computer will be very helpful.
As part of this week's exercise in Chapter 3, you must post a screenshot of your StampPlot showing the D.C. LoadLine and Power Dissipation Curve of the Bipolar Transistor. A sample post is included in the Reply below. Be sure to answer all questions in the chapter and you should be able to understand all of the calculations presented.
For your convenience, a pdf of just Chapter 3 is attached here: Be sure to use the right StampPlot macros and BS2 programs for each activity.
Some of the experiments in this chapter and throughout the rest of the text will make use of the ADC0831 Analog-to-Digital Converter chip. Here is the data sheet:
This week's lab exercise is to continue working in the Process Control text. You should have read and worked through Chapters 1 & 2 last week. If not, do so FIRST!!!
NOTE: StampPlot software IS NOT permanently installed on the computers in our lab. You need to follow the directions given in Week #9 and install it on your own computer or have your professor install it on the computer you are going to use. It is highly recommended that you install it on your own computer as you will be using StampPlot regularly for the rest of this course and creating numerous screenshots and files. Having this installed on your own computer will be very helpful.
As part of this week's exercise in Chapter 3, you must post a screenshot of your StampPlot showing the D.C. LoadLine and Power Dissipation Curve of the Bipolar Transistor. A sample post is included in the Reply below. Be sure to answer all questions in the chapter and you should be able to understand all of the calculations presented.
For your convenience, a pdf of just Chapter 3 is attached here: Be sure to use the right StampPlot macros and BS2 programs for each activity.
Some of the experiments in this chapter and throughout the rest of the text will make use of the ADC0831 Analog-to-Digital Converter chip. Here is the data sheet:
-
- Posts: 30
- Joined: Fri Sep 06, 2019 9:47 am
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
Chapter 3 work
Verified RJ 4/20/21
Verified RJ 4/20/21
- Attachments
-
- Chapter 3 part 2.jpg (68.68 KiB) Viewed 5781 times
-
- Chapter 3 part 3.jpg (63.39 KiB) Viewed 5781 times
-
- Chapter 3 part 1.jpg (63.55 KiB) Viewed 5781 times
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
NAING , WEEK 10 BS2 AND Stamp Plot
Verified RJ 4/20/21
Verified RJ 4/20/21
- Attachments
-
- Plot Select04-13_at_13-03-10.jpg (74.23 KiB) Viewed 5752 times
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
NAING ONG EET-250L WEEK 10
Verified RJ 4/20/21
Verified RJ 4/20/21
- Attachments
-
- Screenshot 2021-04-15 100932.png (65.05 KiB) Viewed 5749 times
-
- Posts: 34
- Joined: Tue Sep 11, 2018 6:23 pm
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
I wasn't sure which ones to post, so those are all.
Partial screenshots due to incorrect program settings. OK, verified, RJ. 4/20/21
Partial screenshots due to incorrect program settings. OK, verified, RJ. 4/20/21
- Attachments
-
- Data_Mon.jpg (95.22 KiB) Viewed 5731 times
-
- Data_Mon_04-13_at_14-54-31.jpg (106.18 KiB) Viewed 5731 times
-
- Data_Mon_04-13_at_14-54-34.jpg (98.77 KiB) Viewed 5731 times
-
- Data_Mon_04-13_at_14-55-47.jpg (100.33 KiB) Viewed 5731 times
-
- Data_Mon_04-13_at_14-56-00.jpg (99.41 KiB) Viewed 5731 times
-
- Data_Mon_04-13_at_14-56-02.jpg (99.48 KiB) Viewed 5731 times
-
- Data_Mon_04-13_at_14-56-03.jpg (94.95 KiB) Viewed 5731 times
-
- Data_Mon_04-20_at_10-49-35.jpg (95.88 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-54-03.jpg (96.95 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-54-18.jpg (101.57 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-54-32.jpg (106.18 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-54-47.jpg (78.36 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-55-02.jpg (92.91 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-55-17.jpg (95.91 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-55-32.jpg (100.49 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-55-47.jpg (100.33 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-55-48.jpg (100.33 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-56-03.jpg (99.48 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-56-17.jpg (96.28 KiB) Viewed 5731 times
-
- Data_Mon_msg.txt_04-13_at_14-56-32.jpg (92.91 KiB) Viewed 5731 times
-
- Posts: 34
- Joined: Tue Sep 11, 2018 6:23 pm
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
Chp.3
Verified RJ 4/20/21
Verified RJ 4/20/21
- Attachments
-
- Light_level.jpg (57.58 KiB) Viewed 5731 times
-
- Load_Line.jpg (60.26 KiB) Viewed 5731 times
-
- Load_Line_04-20_at_11-05-53.jpg (107.43 KiB) Viewed 5731 times
-
- Load_Line_04-20_at_11-09-38.jpg (107.39 KiB) Viewed 5731 times
-
- Posts: 36
- Joined: Wed Sep 04, 2019 10:05 am
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
Process control Chap 3
- Attachments
-
- 2021-04-13 (2).png (776.92 KiB) Viewed 5716 times
-
- 2021-04-13 (3).png (775.23 KiB) Viewed 5716 times
-
- 2021-04-13.png (753.06 KiB) Viewed 5716 times
-
- 2021-04-13 (1).png (748.43 KiB) Viewed 5716 times
-
- 2021-04-15.png (772.81 KiB) Viewed 5716 times
-
- 2021-04-22 (4).png (787.83 KiB) Viewed 5716 times
-
- 2021-04-22 (1).png (782.68 KiB) Viewed 5716 times
-
- 2021-04-22 (2).png (801.9 KiB) Viewed 5716 times
-
- 2021-04-22 (3).png (810.61 KiB) Viewed 5716 times
-
- 2021-04-22.png (777.72 KiB) Viewed 5716 times
-
- Posts: 20
- Joined: Fri Sep 06, 2019 9:51 am
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
wk 10
- Attachments
-
- Plot Select04-13_at_13-03-10.jpg (74.23 KiB) Viewed 5678 times
-
- Screenshot 2021-04-15 100932.png (65.05 KiB) Viewed 5678 times
-
- Posts: 38
- Joined: Fri Sep 06, 2019 9:46 am
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
mmlopez0002
- Attachments
-
- 1.jpg (60.8 KiB) Viewed 5674 times
-
- Data_Mon04-15_at_12-56-19.jpg (59.75 KiB) Viewed 5674 times
-
- Data_Mon04-15_at_13-05-36.jpg (61.44 KiB) Viewed 5674 times
-
- Data_Mon04-15_at_14-03-51.jpg (55.72 KiB) Viewed 5674 times
-
- Data_Mon04-15_at_14-06-19.jpg (57.12 KiB) Viewed 5674 times
-
- Load_Line_04-29_at_09-25-44.jpg (104.74 KiB) Viewed 5674 times
-
- Load_Line_04-29_at_09-35-41.jpg (95.46 KiB) Viewed 5674 times
-
- Load_Line_04-29_at_09-41-37.jpg (103.1 KiB) Viewed 5674 times
-
- SIC Process Control -- Light Level Plot.jpg (57.03 KiB) Viewed 5674 times
-
- Posts: 48
- Joined: Tue Sep 18, 2018 6:10 pm
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
ch3
- Attachments
-
- Data_Mon - Copy (2).jpg (169.39 KiB) Viewed 5659 times
-
- Data_Mon - Copy (3).jpg (172.34 KiB) Viewed 5659 times
-
- Data_Mon - Copy.jpg (64.63 KiB) Viewed 5659 times
-
- Data_Mon.jpg (61.98 KiB) Viewed 5659 times
-
- Data_Mon1.jpg (59.16 KiB) Viewed 5659 times
-
- Posts: 48
- Joined: Tue Sep 18, 2018 6:10 pm
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
Tran DC Load Line
- Attachments
-
- Load_Line.jpg (174.84 KiB) Viewed 5658 times
-
- Posts: 27
- Joined: Fri Sep 06, 2019 9:43 am
Re: Week #10: (3/29-4/2) Parallax Process Control - Week #2
Chapter 3 Work