This week we are going to jump to Chapter 6 in the Process Control text and progress from this chapter throughout the completion of the Incubator circuit exercises. This will probably take about 3 weeks or so.
You need to start Chapter #6 this week to give you enough time to complete the Incubator Circuit & Exercises used throughout the rest of the text. The Incubator Experiments are a critical part of the course.
Again, you should begin Chapter 6 this week.
There are some helpful documents from Chapter 6 attached below, and printed copies will be available for you in the lab if you prefer.
Post your progress and screenshots for Week #10 as a reply to this Topic.
Week #10 (3/27-31): Parallax Process Control - Week #3
-
- Posts: 2380
- Joined: Fri Sep 04, 2015 6:59 pm
Week #10 (3/27-31): Parallax Process Control - Week #3
- Attachments
-
- Annotated_Ch. 6 & 7 Incubator Schematic & Layout v23.2.pdf
- (2.02 MiB) Downloaded 116 times
-
- Posts: 62
- Joined: Thu Sep 08, 2022 3:24 pm
Re: Week #10 (3/27-31): Parallax Process Control - Week #3
completed week 10
- Attachments
-
- heater.jpg (81.72 KiB) Viewed 2534 times
-
- Posts: 65
- Joined: Thu Sep 08, 2022 10:49 pm
Re: Week #10 (3/27-31): Parallax Process Control - Week #3
Incubator Lab
- Attachments
-
- 2023-04-04.png (219.1 KiB) Viewed 2516 times
-
- Posts: 65
- Joined: Fri Sep 10, 2021 2:30 pm
Re: Week #10 (3/27-31): Parallax Process Control - Week #3
I completed week #10 Incubator Lab
- Attachments
-
- Span_Offset not sure if works proper.jpg (95.04 KiB) Viewed 2515 times
-
- Inc_Open_loop.jpg (114.81 KiB) Viewed 2515 times
-
- Data_Mon_5_B.jpg (94.71 KiB) Viewed 2515 times
-
- Posts: 59
- Joined: Tue Nov 09, 2021 9:12 am
Re: Week #10 (3/27-31): Parallax Process Control - Week #3
Vlad Seleznev
- Attachments
-
- 2023-04-04.png (219.1 KiB) Viewed 2441 times
-
- Posts: 48
- Joined: Fri Sep 09, 2022 12:30 am
Re: Week #10 (3/27-31): Parallax Process Control - Week #3
Completed Week 10
- Attachments
-
- Screenshot 2023-04-06 143956.png (662.37 KiB) Viewed 2428 times
-
- Screenshot 2023-04-06 145454.png (648.33 KiB) Viewed 2428 times
-
- Posts: 63
- Joined: Thu Sep 23, 2021 9:12 am
Re: Week #10 (3/27-31): Parallax Process Control - Week #3
Paula Garcia Week 10 Worked with Riley S.
- Attachments
-
- Screenshot 2023-05-11 at 8.20.46 PM.png (838.59 KiB) Viewed 2416 times
-
- Screenshot 2023-05-11 at 8.21.01 PM.png (827.95 KiB) Viewed 2416 times
Re: Week #10 (3/27-31): Parallax Process Control - Week #3
Week 10
- Attachments
-
- Data_Mon_5_B(1).jpg (94.71 KiB) Viewed 2404 times
-
- Inc_Man.jpg (98.67 KiB) Viewed 2404 times
-
- Inc_Open_loop.jpg (114.81 KiB) Viewed 2404 times