Week #13 (4/17-21) Weekly Progress Report

Post Reply
rjagodowski
Posts: 2393
Joined: Fri Sep 04, 2015 6:59 pm

Week #13 (4/17-21) Weekly Progress Report

Post by rjagodowski »

Post your progress, contributions, work and anything else you did for the Team project here.

There will be a separate Topic for each week during the semester.

These are individual posts, so each member must post their own progress report. If you worked with others, or the entire group, then you can mention that in your post as well. But each member must post to receive credit for this week's post.
rpoznyur2101
Posts: 65
Joined: Thu Sep 08, 2022 10:49 pm

Re: Week #13 (4/17-21) Weekly Progress Report

Post by rpoznyur2101 »

This week went very well! Greytton and Joe worked on the fanuc and plc, Vlad worked on some 3d printed part. Rigo assembled the ramps together. Jake was able to help out with the pvc section of the project. I cut a hole inside one of the pvc holes, cut a bigger hole in a 3d printed part, and did some more wood cutting.
jhgirouard2101
Posts: 62
Joined: Thu Sep 08, 2022 3:24 pm

Re: Week #13 (4/17-21) Weekly Progress Report

Post by jhgirouard2101 »

Tested some more final positions for the hopper/ conveyor along with more PLC work. Vlad printed out the EOAT for the Fanuc.
Jbraco0001
Posts: 44
Joined: Fri Sep 06, 2019 9:43 am

Re: Week #13 (4/17-21) Weekly Progress Report

Post by Jbraco0001 »

this week Greyton and I got the HMI working nice.
reespinoza2101
Posts: 29
Joined: Thu Sep 22, 2022 12:07 am

Re: Week #13 (4/17-21) Weekly Progress Report

Post by reespinoza2101 »

I was able to get the ramps togethor and mounting and and placing the stepper motor for the ramp and on the placements for them in the final project as well and mess with some 3D prints with Vlad for the stepper motor and redesigning our boxes as we can to a little issue
Post Reply

Return to “Progress Reports for Golfball Group”