Constructed rollers for the end. Started testing and ran into some issues. Going to construct rollers out of PVC. Milk carton keep tipping over.
-
- Posts: 35
- Joined: Mon Sep 18, 2023 2:11 pm
Re: Week #5 (2/19-23): Progress Reports
T:
We were at a slight standstill early this week waiting for parts and doing some design changes. I started working on working out how the raspberry pi will interface with the PLC.
th:
We got the raspberry pi and I spent most of the period trying to get it to work, we also got some of the laser break sensors. We will need to make more of them using LEDs and light sensors from the boebot kit. I believe we will need several more changes to the design before we can have a fully functional system planned out.
We were at a slight standstill early this week waiting for parts and doing some design changes. I started working on working out how the raspberry pi will interface with the PLC.
th:
We got the raspberry pi and I spent most of the period trying to get it to work, we also got some of the laser break sensors. We will need to make more of them using LEDs and light sensors from the boebot kit. I believe we will need several more changes to the design before we can have a fully functional system planned out.
-
- Posts: 55
- Joined: Mon Feb 20, 2023 8:48 am
Re: Week #5 (2/19-23): Progress Reports
Had some problems when we started testing the rollers. Started discussing a new plan for it.
-
- Posts: 39
- Joined: Tue Dec 19, 2023 12:10 pm
Re: Week #5 (2/19-23): Progress Reports
We figured out that the rollers idea did not work. So we made a new idea where the carton slides down and works well. Brainstorming ideas for how and where to make a loading platform. Alos made a platform for first conveyor.
DS
DS
-
- Posts: 31
- Joined: Fri Sep 23, 2022 6:21 pm
Re: Week #5 (2/19-23): Progress Reports
went through the manuals to find the estop to clear the fault, tried different ways to jump the wires to clear the fault but it sill gives the fault.
-
- Posts: 41
- Joined: Tue Dec 19, 2023 12:31 pm
Re: Week #5 (2/19-23): Progress Reports
worked on program for plc and raspberry pi. re-wired power supplies and some more ice cube relays to control conveyors and solenoid more efficiently. started planning out 3D print for grabber for fanuc.